The 7 Wastes – “Muda”
|
Definition
|
Examples
|
Causes
|
Countermeasures
|
|
Over-|production
|
Producing more than the customer needs right now
|
Producing product to stock based on sales forecasts
Producing more to avoid set-ups
Batch process resulting in extra output
|
Forecasting
Long set-ups
“Just in case” for breakdowns
|
Pull system scheduling
Heijunka – level loading
Set-up reduction
TPM
|
|
Trans- portation
|
Movement of product that does not add value
|
Moving parts in and out of storage
Moving material from one workstation to another
|
Batch production
Push production
Storage
Functional layout
|
Flow lines
Pull system
Value Stream organizations
Kanban
|
|
Motion
|
Movement of people that does not add value
|
Searching for parts, tools, prints, etc.
Sorting through materials
Reaching for tools
Lifting boxes of parts
|
Workplace disorganization
Missing items
Poor workstation design
Unsafe work area
|
5S
Point of Use Storage
Water Spider
One-piece flow
Workstation design
|
|
Waiting
|
Idle time created when material, information, people, or equipment is not ready
|
Waiting for parts
Waiting for prints
Waiting for inspection
Waiting for machines
Waiting for information
Waiting for machine repair
|
Push production
Work imbalance
Centralized inspection
Order entry delays
Lack of priority
Lack of communication
|
Downstream pull
Takt time production
In-process gauging
Jidoka
Office Kaizen
TPM
|
|
Processing
|
Effort that adds no value from the customer’s viewpoint
|
Multiple cleaning of parts
Paperwork
Over-tight tolerances
Awkward tool or part design
|
Delay between processing
Push system
Customer voice not understood
Designs “thrown over the wall”
|
Flow lines
One-piece pull
Office Kaizen
3P
Lean Design
|
|
Inventory
|
More materials, parts, or products on hand than the customer needs right now
|
Raw materials
Work in process
Finished goods
Consumable supplies
Purchased components
|
Supplier lead-times
Lack of flow
Long set-ups
Long lead-times
Paperwork in process
Lack of ordering procedure
|
External kanban
Supplier development
One-piece flow lines
Set-up reduction
Internal kanban
|
|
Defects
|
Work that contains errors, rework, mistakes or lacks something necessary
|
Scrap
Rework
Defects
Correction
Field failure
Variation
Missing parts
|
Process failure
Mis-loaded part
Batch process
Inspect-in quality
Incapable machines
|
GembaSigma
Pokayoke
One-piece pull
Built-in quality
3P
Jidoka
|